Last updated: 14 June 2026  ·  Originally published: 1 June 2026

Quick Answer

Building a garage in Melbourne costs $18,000–$60,000+ in 2026 depending on size, materials, and finish. A single garage (3m×6m) costs $18,000–$35,000 supplied + built. A double garage (6m×6m) runs $28,000–$55,000. A triple garage (9m×6m) $45,000–$75,000. Adding a granny flat / studio above roughly doubles the cost ($85,000–$160,000 total). A council building permit is required for any garage over 10m² in Victoria. Most builds take 6–12 weeks from permit issue to lock-up.

Garage build illustration
Garage build illustration

Complete Cost Breakdown

Cost by Garage Size and Type

Garage Type + Size Supplied + Built Typical Inclusions
Single garage (3m×6m) — Colorbond kit $18,000–$25,000 Slab + frame + roller door + 1 personal door
Single garage (3m×6m) — brick veneer $26,000–$35,000 Slab + brick walls + tile roof + 2 doors
Double garage (6m×6m) — Colorbond $28,000–$42,000 Slab + frame + 2 roller doors + window
Double garage (6m×6m) — brick veneer $38,000–$55,000 Brick + Colorbond roof + 2 sectional doors
Triple garage (9m×6m) — Colorbond $42,000–$58,000 Larger slab + 3 roller doors + ventilation
Triple garage (9m×6m) — brick veneer $55,000–$75,000 Full bricks + Colorbond/tile + 3 sectional
Garage with apartment / studio above $85,000–$160,000 Add 1-bedroom dwelling, plumbing, electrical, council DA
Detached workshop garage (6m×9m) $45,000–$70,000 Higher ceiling, 3-phase power, concrete pad

Cost Breakdown by Component

Component Cost Notes
Site preparation / excavation $1,500–$5,500 Depends on slope, soil type
Concrete slab (per m²) $120–$220 Includes reinforcement, formwork
Frame (timber or steel) $3,500–$8,500 Steel slightly more, longer span possible
Brick or block walls $220–$380 per m² Bricks + labour for veneer construction
Colorbond cladding $60–$110 per m² Wall sheets + flashings + fixings
Roof (Colorbond) $80–$140 per m² Sheets + trusses + insulation
Roof (concrete tile) $110–$180 per m² Heavier; needs stronger trusses
Roller door (single) $1,200–$2,400 Manual or motorised
Sectional door (single) $1,800–$3,800 Quieter, better insulation
Personal door + frame $450–$900 Side access door
Window (1.2m×0.9m) $280–$650 Aluminium frame standard
Electrical rough-in + 4 outlets $1,800–$3,500 Licensed electrician + permit
Plumbing (if including sink/toilet) $3,500–$8,000 Licensed plumber + Council
Council building permit $450–$1,200 Permit fee + assessment
Planning permit (if needed) $1,500–$4,500 Required if outside DCP standards
Engineering certification $650–$1,500 Required for slab + frame
Insurance (during build) $300–$650 Domestic Building Insurance
Pro tip: Steel-frame Colorbond garages are 20–30% cheaper than brick veneer and can be built in 3–4 weeks vs 8–12 weeks for brick. Brick veneer adds resale value and matches the existing home better — calculate cost vs sale uplift before committing.

Permit Costs and Requirements (Victoria 2026)

Garage Size / Type Permit Required? Cost
Under 10m² (small shed) No permit needed
10–40m² single garage Building permit only $450–$900
40–60m² double garage Building permit + may need planning $650–$2,500
Over 60m² or two-storey Building + planning permit $2,000–$5,500
Garage in heritage overlay area Heritage permit + building permit $2,500–$6,500
Garage near or over easement Building permit + utility approval $1,200–$3,500
Garage build illustration
Garage build illustration

What Affects Garage Build Cost

1. Wall Material (Brick vs Colorbond)

Colorbond / steel garages are the cheapest option ($18,000–$30,000 for single, $28,000–$45,000 for double). Brick veneer adds $8,000–$15,000 to a single, $12,000–$20,000 to a double, but matches existing weatherboard or brick homes and adds 5–10% more to property value.

2. Roof Type

Colorbond roof is standard at $80–$140/m². Concrete tile roof matches existing tile homes but adds $30–$50/m² plus stronger trusses. Don’t underestimate roof load — tile garages need engineering-certified frames.

3. Door Type

Standard roller doors are cheapest ($1,200–$2,400 single). Sectional doors look better, insulate better, and run quieter but cost 50–80% more. Tilt doors are between, manual or motorised. For a double garage, two single doors offer flexibility but two sectionals look more modern.

4. Slab Size and Site Conditions

A flat block with no rock takes a slab in 1 day. A sloping block needs cut-and-fill, retaining, or stepped foundations — add $3,000–$8,000. Rock requires excavation rates of $200–$450 per cubic metre.

5. Electrical and Plumbing

Basic electrical (5 outlets, lighting) is $1,800–$3,500. Adding sink + toilet for workshop / studio use needs licensed plumbing ($3,500–$8,000) plus Council connection fees. 3-phase power for workshop equipment adds $1,500–$3,500.

6. Insulation and Finishes

Unlined Colorbond walls/roof are cheapest but condensation-prone. R2.0 wall insulation + R3.5 roof insulation adds $1,500–$3,500. Plastered linings for habitable workshop add $4,500–$9,000. Painted internal walls add $1,200–$2,500.

7. Council Permit Path

Most metropolitan Melbourne councils accept ResCode-compliant garages with building permit only (faster, $450–$900). Garages exceeding boundary setbacks, lot coverage, or visual amenity provisions need planning permit (4–12 weeks longer + $1,500–$4,500).

8. Add-Ons (Apartment / Studio / Workshop Above)

Garage with a studio/granny flat above (legally a “Dependent Person’s Unit” under Victorian planning rules) roughly doubles the cost. Expect $85,000–$160,000 total — full bathroom, kitchen, separate entry, additional planning permits, sewer connection, fire separation. Often more cost-effective than separate granny flat.

Garage build illustration
Garage build illustration

Double Garage Cost Melbourne — Dedicated Breakdown

A standard double garage (6m×6m / 36m²) is the most common new build size in Melbourne in 2026 — large enough for two cars plus a workshop bench or storage. Here’s the dedicated breakdown for double-garage builds.

Double Garage Cost by Build Type

Build Type (6m × 6m / 36m²) Total Supplied + Built What’s Included
Basic Colorbond kit, DIY-assist $18,000–$26,000 Slab + frame + Colorbond cladding + standard roller door + permit. No insulation or lining.
Standard Colorbond, turnkey $28,000–$42,000 Above + sectional door + 1 PA door + power + lights + 1 window
Brick veneer to match house $42,000–$58,000 Brick walls + Colorbond or tile roof + matching trim + sectional door + power
Premium with insulation + lining $48,000–$68,000 Above + R3.5 insulation + plasterboard lining + epoxy floor + remote sectional door
Heritage-area build (Carlton, Fitzroy) $55,000–$85,000 Above + heritage facade compliance + slate or terracotta roof

Double Garage Cost by Component

Component (for 6m×6m) Cost Notes
Concrete slab (36m², reinforced) $6,500–$11,500 $180–$320/m² including excavation, reo, pump
Wall frames (steel) $4,500–$7,500 Steel portal frame, more durable than timber
Wall frames (timber) $3,500–$5,500 Pine treated, cheaper but more maintenance
Colorbond wall cladding $2,800–$4,500 Standard colours, includes flashings
Brick veneer cladding $8,500–$14,500 To match house, includes bricklayer labour
Colorbond roof (with sarking) $3,200–$5,500 Includes sarking, ridge, gutters, downpipes
Sectional roller door (standard, manual) $1,800–$2,800 5m wide x 2.1m tall, single skin steel
Sectional roller door (insulated, remote) $2,800–$4,500 Insulated, remote opener, sectional panels
Tilt panel or premium door (panel-lift) $3,500–$6,500 Cedar look, contemporary styling
PA (personal access) door $650–$1,200 Single hinged door, lockable
Window (1.2m x 0.9m) $450–$850 Aluminium-framed, fixed or sliding
Power (2 x double GPO + 1 light circuit) $1,200–$2,200 Includes RCD, conduit, sub-board if needed
LED battens (4 x 1.2m) $280–$550 Standard workshop lighting
Insulation + lining (R3.5 walls + ceiling) $3,500–$5,500 Plasterboard lined, painted
Epoxy floor coating $1,800–$3,200 $50–$90/m² for solvent-based
Council permit + drawings $1,500–$3,500 Higher in heritage overlays
Driveway extension $2,500–$6,500 If existing crossover insufficient

Double Garage vs Single Garage — Is It Worth the Upgrade?

Going from single (3m×6m / 18m²) to double (6m×6m / 36m²) typically adds $8,000–$15,000 to the build cost — but it doubles the usable floor area. Cost per square metre actually drops because slab, permit, roof, and labour costs don’t double linearly.

Garage size Floor area Typical build cost $/m²
Single (3m×6m) 18m² $18,000–$35,000 $1,000–$1,950
Double (6m×6m) 36m² $28,000–$55,000 $780–$1,530
Triple (9m×6m) 54m² $45,000–$75,000 $830–$1,390

The double is the sweet spot — best $/m² for most Melbourne suburban lots, and aligns with what buyers expect to find when selling. Single garages are often a resale negative in family suburbs (Berwick, Pakenham, Officer, Cranbourne); doubles are neutral-to-positive.

Double Garage Timeline

  • Weeks 1–3: Designer/draftsperson preps plans, energy report, soil test
  • Weeks 4–8: Council permit (longer in heritage overlay areas)
  • Week 9: Site prep, slab pour, 7-day cure
  • Week 10: Frame, roof, cladding
  • Week 11: Door, electrical, finishing
  • Week 12: Final inspection, certificate of occupancy

Total: 10–14 weeks from signed contract to keys, weather permitting.

Hidden Costs Specific to Double Garages

  • Driveway widening — an existing single-car crossover usually needs widening to fit the double. Council crossover application costs $750–$1,800, civil works $2,500–$6,500.
  • Stormwater easement — larger roof means larger downpipes, may need new stormwater connection. $850–$2,200.
  • Energy efficiency report — any habitable lining or window over 1.5m² triggers Section J energy compliance. $250–$650.
  • Two-car turning circle — if the lot is tight, you may need additional paving for swing-in turning. $1,500–$4,500.
Pro tip: The $5,000–$8,000 you’d spend on insulation + lining + epoxy floor turns the double garage into a part-time workshop or man-cave / she-shed without the cost of building a separate room. Doing this at build time is 40–60% cheaper than retrofitting later.

Build Timeline (Typical Melbourne Project)

Phase Duration What Happens
Design + plans 2–4 weeks Drafter or builder produces plans + engineering
Permits 4–12 weeks Council building permit (planning permit adds weeks)
Site prep + slab 1–2 weeks Excavation, formwork, pour, cure
Frame + roof 1–2 weeks Walls up, roof on (lock-up)
Cladding + doors 1 week External finishes, doors installed
Electrical + plumbing rough-in 3–5 days Conduit, wiring, pipework before linings
Internal linings + paint 1–2 weeks If habitable / workshop fit-out
Final inspections + occupancy 1–2 weeks Building surveyor + Council sign-off
Total (basic Colorbond) 6–10 weeks From plans to keys
Total (brick + studio above) 16–24 weeks From plans to occupancy

DIY vs Hire a Builder

Garage construction in Victoria is regulated — structural framing, electrical work, plumbing all require licensed trades under the Building Act 1993. DIY scope is limited to:

  • Site prep + landscaping work (no excavation under 1m depth)
  • Concrete slab IF you’re a registered builder OR you engage one for sign-off
  • External painting + minor finishes after handover
  • Internal fit-out (shelving, workbench, organisation)

Engaging a registered builder for the whole project is the standard approach and what insurers/conveyancers expect. Owner-builder permits are legal but require 6-day course, OB-WHS plan, additional insurance, and shift liability to you.

Safety warning: Unpermitted garages reduce resale value by 5–15% and may need full demolition if discovered by a buyer’s surveyor. Always pull the building permit before pouring slab — retrospective permits cost 3× the original and aren’t always granted.
Garage build illustration
Garage build illustration

Top 10 Tips and Gotchas

  1. Always get 3 quotes from registered builders. Variance is 30–60% for the same brief. Check Victorian Building Authority licence numbers.
  2. Get the building permit BEFORE pouring the slab. Retrospective permits cost more, take longer, and may not be granted.
  3. Check boundary setbacks. Most Melbourne councils require 1m side + 3m rear setback for non-attached garages. Some allow 0m with neighbour consent.
  4. Plan for power BEFORE the slab. Conduit must be in the slab or under it — retrofit is expensive.
  5. Don’t skip Domestic Building Insurance. Required by law for jobs over $16,000 — protects you if builder fails.
  6. Verify width for car door clearance. Standard single garage is 3m wide; allow 3.2m minimum for comfortable door opening. Double garage 6m is tight — 6.4m better.
  7. Specify the door type carefully. Sectional doors look modern + insulate better; roller doors cheaper. Both motorised options add $400–$800.
  8. Plan for natural light. One window per garage bay halves daytime electrical use. Whirlybird vent + skylight prevents heat buildup.
  9. Check the soil type. Reactive clay (common in SE Melbourne suburbs) needs deeper footings or piers — adds $1,500–$4,000.
  10. Plan storage from day one. Built-in shelving designed during framing costs 60% less than retrofitted after lock-up.
Garage build illustration
Garage build illustration

Local Melbourne Resources

FAQ

How much does it cost to build a single garage in Melbourne?

A single garage (3m×6m) in Melbourne costs $18,000–$25,000 for a Colorbond steel kit garage supplied + built, or $26,000–$35,000 for a brick veneer match to your existing home. Add $1,200–$2,400 for a motorised roller door, $1,800–$3,500 for basic electrical, and $450–$900 for the council building permit.

How much does a double garage cost to build?

A standard double garage (6m×6m, 36m²) costs $28,000–$42,000 in Colorbond steel or $38,000–$55,000 in brick veneer in 2026 Melbourne. Add $1,500–$3,500 for electrical, $450–$1,200 for permits, and $300–$650 for builder’s insurance. Total typically lands at $32,000–$48,000 for steel or $45,000–$65,000 for brick.

Do I need a council permit for a garage in Melbourne?

Yes, for any garage over 10m² under Victorian Building Regulations. A building permit ($450–$1,200) is required. A planning permit ($1,500–$4,500 extra) is needed if the garage exceeds ResCode standards (setbacks, lot coverage, visual amenity). Heritage overlay areas always need additional approval.

How long does it take to build a garage in Melbourne?

From design to keys: 6–10 weeks for a basic Colorbond garage, 10–16 weeks for brick veneer, 16–24 weeks for garage with studio/granny flat above. Permits often consume 4–12 weeks of that — budget extra time if your block needs a planning permit.

Is it cheaper to build a garage or convert an existing structure?

Building new is usually cheaper than converting unless the existing structure already has slab, walls, and roof at suitable spec. Converting a carport to enclosed garage adds $8,000–$18,000 (walls, doors, electrical). Converting a shed adds $15,000–$30,000 (engineering, foundations, doors, council compliance). Building fresh is faster and predictable.

Can I add an apartment or studio above my garage?

Yes — legally classified as a Dependent Person’s Unit under Victorian planning rules. Typical cost is $85,000–$160,000 for the garage + 1-bedroom studio combined, requiring building + planning permits, sewer connection, fire separation, and engineering certification. Many councils accept this as an alternative to separate granny flats with similar approval times.

What’s the cheapest way to build a garage in Melbourne?

A Colorbond steel kit garage (single 3m×6m) at $18,000–$22,000 supplied + erected is the cheapest legal option. Kit garages from Bunnings or specialised suppliers include all frames, sheets, doors, and fixings — only slab + electrical + permits are extra. Total minimum spend: ~$22,000–$27,000 all-in.

Final Thoughts

Building a garage is one of the higher-ROI additions to a Melbourne home — it adds 5–10% to property value, protects vehicles from sun/storm damage, and creates flexible storage/workshop space.

Here’s the bottom line:

  • Single Colorbond garage: $18,000–$25,000 supplied + built
  • Double Colorbond garage: $28,000–$42,000
  • Triple Colorbond garage: $42,000–$58,000
  • Garage + studio above: $85,000–$160,000
  • Always get 3 quotes from VBA-registered builders
  • Pull the building permit BEFORE pouring slab — retrospective permits cost 3×
  • Plan for power, lighting, and storage during the design phase — retrofit is expensive

Pair this work with: carport vs garage comparison, driveway cost guide, and EV charger installation — build them together to save on combined trades and permits.

See also on HomeUpkeep: